Project Management Process
All of the following will occur during project initiating EXCEPT :
The project scope statement is an output of the Define Scope process and is part of the planning process group.
Which of the following process group consists of the processes to complete the work defined in the project management plan and ultimately satisfies the project specifications and objectives ?
The executing process group is intended to ensure that the work defined in the project plan is performed.
All of the following should be done during the closing process group EXCEPT :
Customer acceptance criteria are determined during initiating process group.
Which of the following process group serve as input to each other ?
The executing process group and the Monitoring & Controlling processes group serve as inputs to each other. The planning process group also feed each other.
Which one of the following is NOT a planning process ?
Develop project team is a process in the executing group. All three remaining processes belong to the planning process group.
Which of the following normally provides the summary milestone schedule ?
A business case, project requirements document, and the project scope statement do not include a summary milestone. Only project charter has it so this is the right choice.
Which one of the following process group consists of iterative and ongoing processes to establish the total scope of effort, to define the project the objectives, and to identify the course of action required to attain those objectives ?
The planning process group and consists of iterative and ongoing processes to establish the total scope of effort, to define the objectives, and to identify the course of action required to attain those objectives.
In which process group does the team track, measure, inspect, monitor, verify, review, compare, and regulate the progress and performance of the project; ensure that plan is working; identify any areas in which changes to the plan are required; and initiate the corresponding changes ?
During the monitoring & controlling process group, project performance is measured and analyzed, and needed changes are identified and approved.
The sponsor has just signed the project charter and assigned you as a project manager to oversee a project to implement a simulator for a local golf club. What would you do FIRST as the project manager ?
The project charter is created, and the project manager is assigned during the initiating process group. Stakeholder identification is also started during initiating and carried on throughout the project life cycle. The project manager should focus on identifying the internal and external stakeholders in the project.
A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process ?
If you chose another part of the project management process, you probably forgot that the situation needs to be evaluated by the project manager before recommending a change or beginning integrated change control.