All of the following will occur during project initiating EXCEPT :

Correct

The project scope statement is an output of the Define Scope process and is part of the planning process group.

Incorrect

 

Which of the following process group consists of the processes to complete the work defined in the  project management plan and ultimately satisfies the project specifications and objectives ?

Correct

The executing process group is intended to ensure that the work defined in the project plan is performed.

Incorrect

 

All of the following should be done during the closing process group EXCEPT :

Correct

Customer acceptance criteria are determined during initiating process group.

Incorrect

 

Which of the following  process group serve as input to each other ?

Correct

The executing process group and the Monitoring & Controlling processes group serve as inputs to each other. The planning process group also feed each other.

Incorrect

 

Which one  of the following is NOT a planning process  ?

Correct

Develop project team is a process in the executing group. All three remaining processes belong to the planning process group.

Incorrect

 

Which of the following normally provides the summary milestone schedule ?

Correct

A business case, project requirements document, and the project scope statement do not include a summary milestone. Only project charter has it so this is the right choice.

Incorrect

 

Which one of the following process group consists of iterative and ongoing processes to establish the total scope of effort, to define the project the objectives, and to identify the course of action required to attain those objectives ?

Correct

The planning process group and consists of iterative and ongoing processes to establish the total scope of effort, to define the objectives, and to identify the course of action required to attain those objectives.

Incorrect

 

In which process group does the team track, measure, inspect, monitor, verify, review, compare, and regulate the progress and performance of the project; ensure that plan is working; identify any areas in which changes to the plan are required; and initiate the corresponding changes ?

Correct

During the monitoring & controlling process group, project performance is measured and analyzed, and needed changes are identified and approved.

Incorrect

 

The sponsor has just signed the project charter and assigned you as a project manager to oversee a project to implement a simulator for a local golf club. What would you do FIRST as the project manager ?

Correct

The project charter is created, and the project manager is assigned during the initiating process group. Stakeholder identification is also started during initiating and carried on throughout the project life cycle. The project manager should focus on identifying the internal and external  stakeholders in the project.

Incorrect

 

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process ?

Correct

If you chose another part of the project management process, you probably forgot that the situation needs to be evaluated by the project manager before recommending a change or beginning integrated change control.