This quiz will submit in:






Question 1

Which one of the following is TRUE about power of the project managers in different organizational structure ?




Question 2

4. You are asked by management to select a contract type that will obligate the seller to accept all liability for poor workmanship, engineering errors, and consequential damages in the project. Which of the following contact types will you select ?




Question 3

A project manager wants to determine how his project is doing the end of sixth month. The actual total expense of the project is $720,000. The planned budget for this length of the time was $600,000. He finds that :




Question 4

10. On a product development project , which is taking a totally new approach to product development unprecedented in the industry, what would be the BEST way to develop quality management plan ?




Question 5

9. As a project manager, you are trying to decide the trade-offs between quality and grade in your project. Which one of the following is correct with respect to a product or a service performed ?




Question 6

5. Monitoring specific project result to determine if they comply with relevant quality standards and identifying ways to eliminate causes of inadequate result is :




Question 7

4. Which of the following assess someone's current engagement level in a project ?




Question 8

Which one of the following takes progressive elaboration approach and plans the work in the near term in detail and future work in a higher level ?




Question 9

Which of the following is NOT a typical characteristic of a project management office (PMO) ?




Question 10

10. You are in Plan Risk Responses process of developing options and actions to reduce threats enhance opportunities to your project objectives. The tools & techniques of the  Plan Risk Responses are including :




Question 11

if the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity ?




Question 12

8. Lars is  a project manager overseeing an online age verification application for one of the very important clients for this organization. Three months in the project, Lars got a call from the client who informed him that they would end the contract due to a change in business direction. The client also discussed the compensation that the seller's organization is offering to Lar's organization for the work completed so far. This is an example of which one of the following ?




Question 13

4. You are considering the idea of putting all team member in the same physical location for the first time. All of the following is true about colocation, reporting structure, and other items. Which of the following is not true about co-location  ?




Question 14

Which one the following statement is FALSE about the project management information system (PMIS) ?




Question 15

In what kind of phase-to-phase relationship is a phase planned at a given time and planning for a subsequent phase is carried out as work progresses on the current phase or  deliverables  ?




Question 16

During which part of the project management process is the project scope statement created ?




Question 17

7, Control Quality is the process of monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results. All of the following tools & techniques use in Control Quality EXCEPT :




Question 18

5. You just identified a new external risk during the executing phase that may impact your project positively. What is your first step ?




Question 19

Which document contains the information  that describes how the formal verification and acceptance of the project deliverables will be contained ?




Question 20

3. Formal written correspondence with customer is required when :




Question 21

Which of the following is NOT a tool and technique used in the Define Scope process ?




Question 22

2. A Cost Performance Index (CPI) of 0.89 means :




Question 23

1  . Which of the following is driven by the organization's risk tolerance ?




Question 24

All of the following should be done during the closing process group EXCEPT :




Question 25

6. You are currently managing the team through observing, using issue logs, keeping in touch, providing feedback, completing performance appraisals, resolving issues and conflicts, and though other methods. You are in which of the following human resource management processes ?




Question 26

7. Which of the following is the process of documenting project purchasing decisions, specifying the approach, defining selection criteria to identify potential sellers, and putting together a procurement management plan ?




Question 27

6. A project manager is in the process of making relevant information available to project stakeholders in a timely manner as planned. The project manager is involved in which of the following processes ?




Question 28

8. You asked one of your team member about the schedule variance (SV) for one of the key deliverables. He mentioned that he is behind the schedule but there would not be a cost variance. Which of the following is NOT true in this case ?




Question 29

During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of the work packages ?




Question 30

2. The sender-receiver model is a basic model of communication that demonstrates how information is sent from the sender and how it is received by the receiver. This model is designed to assist project managers and team members in improving their communication skills. This communication model highlights mostly on which one of the following ?




Question 31

9. A project  manager is in Develop Project Team process focusing on enhancing project performance by building a sense of team and improving competencies, team interaction, and overall team environment. While referring to Tuckman's model, she notices that the greatest level of conflict in the five different stages of team building is most likely to appear in which of the following stages :




Question 32

The organization has to make an initial investment of $250,000 with expected cash inflows of $75,000 in the first year and $25,000 per quarter thereafter for the first project. The second project has a payback period of thirty-five months. Which project should the selection committee recommend ?




Question 33

Which one  of the following is NOT a planning process  ?




Question 34

9. You  have been managing a multi-year construction project for one of your most important clients. You requested your lead business analyst to develop a reports that will capture project results for last four years and illustrate whether project performance is improving or deteriorating. You are interested in which of the following reports ?




Question 35

6. At your project, EV = $130,500 ; PV = $125,000 ; and AC = $129,000. Which one the following statement is true ?




Question 36

What is the meaning of Perform Integrated Change Control




Question 37

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process ?




Question 38

3. You are in the project manager of a construction project that will take six months to complete and will cost $75,000 / month. At the end of third month, you are asked to find out the cumulative SPI for the project. While reviewing, you found that you have spent $80,000 in the first month, $72,000 in the second month, and $75,000 in the third month. And also found that project was 15% complete at the end of 1st month, 35 % complete at the end of 2nd month, 45 % complete at the end of 3rd month. If you planned to complete 50% of the work by this time, what is the cumulative SPI at the end of month three ?




Question 39

6. You are planning to hire a third-party to perform a schedule or random structure review to determine whether your quality management activities comply with organizational an project process, policies, and procedures. All of the following will be done in this quality audit EXCEPT :




Question 40

Which one of the following process group consists of iterative and ongoing processes to establish the total scope of effort, to define the project the objectives, and to identify the course of action required to attain those objectives ?




Question 41

1  . A project manager has a problem with a team member's performance. What is the BEST form of communication for addressing this problem ?




Question 42

7. You have identified several problems along with their causes in your web-based application development project. Which one of the following have you probably used to show the problem and its causes and effects ?




Question 43

A project just initiated under a contract in your organization, and you were assigned as the project manager. You were expecting a statement of work (SOW), which will describe the business need, product scope, and other elements. In this case, from whom should you expect the SOW ?




Question 44

9. What is the BEST way to manage stakeholders who are high on power but low on interest ?




Question 45

6. Which of the following should be included in the project charter ?




Question 46

The scope baseline, which consists of the scope statement document, the WBS, and the WBS dictionary, is used as an input in all of the following processes EXCEPT :




Question 47

3. You will be overseeing a project to develop a smartphone application. While analyzing your project, you identify that there is a 55 percent probability of making $120,000, a 45 percent probability losing $55,000. What does $41,250 represent in this case ?




Question 48

10. You were informed by management that an external audit team will be auditing your project to make sure that the project complies with standard organizational project management policies and procedures. During the audit, the key auditor wants to review the training plan for the team members as well as their certification requirements. You should refer the auditor to which of the following ?




Question 49

9. You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting, and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following ?




Question 50

While managing a data recovery project, you are performing the following activities : comparing actual project performance against the project management plan : analyzing, tracking, and monitoring project risks ; assessing performance to determine whether any corrective or preventive actions are required; providing information to support status reporting; monitoring implementation of approved changes; providing forecasts to update current cost and schedule information.       Which process are you in this time?




Question 51

3. Virtual team is a tool for which of the following processes ?




Question 52
  1.  A CPI value of 1.20 and an SPI value of 1.30 for a project mean which of the following ?



Question 53

You are overseeing a data center project, the team members have finished creating WBS and WBS dictionary also completed activity sequencing and submitted their activity duration estimates to you. Recently, you developed the project schedule. What should you be focusing on next ?




Question 54

Which one of following PMO structure mostly provides guidelines, policies, and templates and requires compliances and usually has a moderate level of control over projects and programs ?




Question 55

All of the following are examples of organization process assets EXCEPT :




Question 56

2. The primary purpose of the stakeholder register is :




Question 57

Which of the following is FALSE about analogous estimating ?




Question 58

6. You were asked by your management to investigate the cause of severe cost overrun in the one of the project that was completed last year. You found out that a certain contract was used in project that is considered to be very risky for the buyer as it does not encourage the seller to control costs; rather, it motivates the seller to be inefficient. What sort of contract was used in the project ?




Question 59

10. Stakeholder management necessitates all of the following EXCEPT :




Question 60

Which of the following process group consists of the processes to complete the work defined in the  project management plan and ultimately satisfies the project specifications and objectives ?