This quiz will submit in:






Question 1

3. Virtual team is a tool for which of the following processes ?




Question 2

9. You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting, and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following ?




Question 3

2, When a product or service completely meets customer's requirements :




Question 4

8. You are in the Monitor Risk process of identifying, analyzing, and planning for newly arising risks, keeping track of identified risks, reanalyzing existing risks, monitoring trigger conditions, monitoring residual risks, and reviewing the execution and effectiveness of risk response. Outputs from the Monitor Risk process include all of the following EXCEPT :




Question 5

3. Quality is :




Question 6

8. A project manager overseeing an ERP implementation project planned to distribute large volumes of information about the project to a large audience. He decided to post the information in an online knowledge repository for access at dicreation of stakeholders. This type of communication method is known as :




Question 7

6. You are currently managing the team through observing, using issue logs, keeping in touch, providing feedback, completing performance appraisals, resolving issues and conflicts, and though other methods. You are in which of the following human resource management processes ?




Question 8

9. Which one of the following is FALSE about TCPI ?




Question 9

You are managing a group of related or unrelated projects or programs and other work and achieve specific strategic business objectives and goals. You are a................




Question 10

Project A has net present value (NPV) of $30,000, will take 5 years to complete, and the associated cost $10,000. Project B has NPV of $60,000, will take 3 years to complete, and the associated cost $15,000. Project C has NPV of $80,000, will take 4 years to complete, and the associated cost $40,000.  Which project will you pick ?




Question 11

Which of the following is NOT a typical characteristic of a project management office (PMO) ?




Question 12

7. Your recently took over a project another project manager who left the organization. You find out that the project has a BAC = $45,000; PV = $30,000; cumulative = $25,000 ; cumulative EV = $24,000. You decided to perform a forecasting analysis and calculated the values for EAC, ETC, and VAC. Which of the following is NOT true ?




Question 13

Which of the following is true regarding the project charter ?




Question 14

2. A Cost Performance Index (CPI) of 0.89 means :




Question 15

9. As a project manager, you are trying to decide the trade-offs between quality and grade in your project. Which one of the following is correct with respect to a product or a service performed ?




Question 16

1  . A project manager has a problem with a team member's performance. What is the BEST form of communication for addressing this problem ?




Question 17

10. You are in Plan Risk Responses process of developing options and actions to reduce threats enhance opportunities to your project objectives. The tools & techniques of the  Plan Risk Responses are including :




Question 18

Which one of the following are the unapproved and undocumented changes and what occurs when to the scope are not detected early enough or are not managed ?




Question 19

The organization has to make an initial investment of $250,000 with expected cash inflows of $75,000 in the first year and $25,000 per quarter thereafter for the first project. The second project has a payback period of thirty-five months. Which project should the selection committee recommend ?




Question 20

1  . Which of the following is NOT a tool used to manage the stakeholder engagement ?




Question 21

All of the following will occur during project initiating EXCEPT :




Question 22

3. Formal written correspondence with customer is required when :




Question 23

Which one of the following takes progressive elaboration approach and plans the work in the near term in detail and future work in a higher level ?




Question 24

10. While working on your communication plan, you have  considered several communication technologies to transfer information among project stakeholders. Communication technology will take into account the following factors that can affect the project EXCEPT which one ?




Question 25

4. Cost associated with inspection, laboratory measurements and analysis, machinery maintenance and calibration, field-testing, and procedure checking are examples of which of the following ?




Question 26

Which one f the following is NOT true about the Define Scope process ?




Question 27

Which of the following  process group serve as input to each other ?




Question 28

6. The team has identified several mitigation and contingency action plans to deal with potential risks within the project. Who is responsible for implementing the actions defined by mitigation and the contingency plan in risk management ?




Question 29

9. You  have been managing a multi-year construction project for one of your most important clients. You requested your lead business analyst to develop a reports that will capture project results for last four years and illustrate whether project performance is improving or deteriorating. You are interested in which of the following reports ?




Question 30

Which one of following PMO structure mostly provides guidelines, policies, and templates and requires compliances and usually has a moderate level of control over projects and programs ?




Question 31

6. Which of the following should be included in the project charter ?




Question 32

Which one of the following process group consists of iterative and ongoing processes to establish the total scope of effort, to define the project the objectives, and to identify the course of action required to attain those objectives ?




Question 33

5. You just identified a new external risk during the executing phase that may impact your project positively. What is your first step ?




Question 34

You are overseeing a data center project, the team members have finished creating WBS and WBS dictionary also completed activity sequencing and submitted their activity duration estimates to you. Recently, you developed the project schedule. What should you be focusing on next ?




Question 35

7. You are in the Plan Resource management process to create on overall staffing management  plan by identifying the availability of resources and those resources' skill levels. Which of the following is NOT a tool &  technique in this process ?




Question 36

Sometimes a project coordinator is an assigned role of organization. which of the following statements is NOT true for a project coordinator ?




Question 37

3. You are in the project manager of a construction project that will take six months to complete and will cost $75,000 / month. At the end of third month, you are asked to find out the cumulative SPI for the project. While reviewing, you found that you have spent $80,000 in the first month, $72,000 in the second month, and $75,000 in the third month. And also found that project was 15% complete at the end of 1st month, 35 % complete at the end of 2nd month, 45 % complete at the end of 3rd month. If you planned to complete 50% of the work by this time, what is the cumulative SPI at the end of month three ?




Question 38

3. Which one of the following is NOT true about a cost reimbursable contract ?




Question 39

As a project manager at a consulting firm and recently received a statement of work (SOW) from the client. As your expectation, the SOW should contain or reference which of the following elements ?




Question 40

Which one of following PMO structure mostly serves as project repository., plays a consultative role, and usually has a low level of control over projects and programs ?




Question 41

5. The MOST common cause of conflict on a project are schedules, project priorities, and :




Question 42

Which one of the following estimating techniques uses mathematical models based on historical records from other projects and can produce higher levels of accuracy ?




Question 43

if the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity ?




Question 44

4. Which of the following assess someone's current engagement level in a project ?




Question 45

3. You have thirteen stakeholders in the construction project that you are overseeing. Your initial study about these stakeholders tells you most of them will  actively support your project to be successful, but you have couple of stakeholders who may adversely impact your project. When do you think these stakeholders will have the most influence on your project ?




Question 46

Which of the following is output of Manager Project Knowledge process ?




Question 47

1  . All the following statements about change control are incorrect, EXCEPT :




Question 48

8. You asked one of your team member about the schedule variance (SV) for one of the key deliverables. He mentioned that he is behind the schedule but there would not be a cost variance. Which of the following is NOT true in this case ?




Question 49

1 . A control chart helps the project manager :




Question 50

During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of the work packages ?




Question 51

The scope baseline, which consists of the scope statement document, the WBS, and the WBS dictionary, is used as an input in all of the following processes EXCEPT :




Question 52

8. Lars is  a project manager overseeing an online age verification application for one of the very important clients for this organization. Three months in the project, Lars got a call from the client who informed him that they would end the contract due to a change in business direction. The client also discussed the compensation that the seller's organization is offering to Lar's organization for the work completed so far. This is an example of which one of the following ?




Question 53

4. You reviewed the WBS and an activity must be completed that your team may not have the expertise to accomplish. You find another team who is willing to take on the work and do the job. What risk response did you use ?




Question 54

8. You are in the Manage Stakeholder Engagement process and are focused on meeting and exceeding the stakeholders' expectations by continuously communicating with them, clarifying and resolving their issues., addressing their concerns, and improving project performance by implementing their change requests. Which of the following is a tool & techniques used in this process ?




Question 55

Which of the following is FALSE about analogous estimating ?




Question 56

2. You have just been assigned as project manager for a large telecommunications project. This one year project is about halfway done. The project team consists of 5 sellers and 20 of your company's employees. You want to understand who is responsible for doing what on project. Where would you find such information ?




Question 57

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process ?




Question 58

10. You are the project manager of a network replacement project for a 40-floor office building. You plan to hire a contractor to pull the old cable out and then install the new cable. The work has to be done in such a way to have minimum to zero disruption to the tenant organization during business hour, hence you need to hire a well experience reputed firm. You contracted the procurement department to develop a list of firms that have the capability to do work. What are you referring to ?




Question 59

All of the following should be done during the closing process group EXCEPT :




Question 60

Which document contains the information  that describes how the formal verification and acceptance of the project deliverables will be contained ?