This quiz will submit in:






Question 1

3. Virtual team is a tool for which of the following processes ?




Question 2

1 . A control chart helps the project manager :




Question 3

Which of the following is output of Manager Project Knowledge process ?




Question 4

4. You are considering the idea of putting all team member in the same physical location for the first time. All of the following is true about colocation, reporting structure, and other items. Which of the following is not true about co-location  ?




Question 5

5. If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV) ?




Question 6

4. Cost associated with inspection, laboratory measurements and analysis, machinery maintenance and calibration, field-testing, and procedure checking are examples of which of the following ?




Question 7

4. You are asked by management to select a contract type that will obligate the seller to accept all liability for poor workmanship, engineering errors, and consequential damages in the project. Which of the following contact types will you select ?




Question 8

While working with your team members on activity sequencing, a team member identifies that a series of activity sequencing method may be utilized in this situation ?




Question 9

3. You will be overseeing a project to develop a smartphone application. While analyzing your project, you identify that there is a 55 percent probability of making $120,000, a 45 percent probability losing $55,000. What does $41,250 represent in this case ?




Question 10

Which one of the following is TRUE about power of the project managers in different organizational structure ?




Question 11

8. Lars is  a project manager overseeing an online age verification application for one of the very important clients for this organization. Three months in the project, Lars got a call from the client who informed him that they would end the contract due to a change in business direction. The client also discussed the compensation that the seller's organization is offering to Lars' organization for the work completed so far. This is an example of which one of the following ?




Question 12

While reviewing one of the activities of team member, you found out that the activity has an early start of days 5, an early finish of day 12, a late start of day 15, and a late  finish of 22 day. The team member tells you that he needs an additional four days to complete the activity due to various reasons he can think of. Which one of the following statements is TRUE ?




Question 13

8. A project manager overseeing an ERP implementation project planned to distribute large volumes of information about the project to a large audience. He decided to post the information in an online knowledge repository for access at dicreation of stakeholders. This type of communication method is known as :




Question 14

Which document contains the information  that describes how the formal verification and acceptance of the project deliverables will be contained ?




Question 15

Which one  of the following is NOT a planning process  ?




Question 16

4. You reviewed the WBS and an activity must be completed that your team may not have the expertise to accomplish. You find another team who is willing to take on the work and do the job. What risk response did you use ?




Question 17

Sometimes a project coordinator is an assigned role of organization. which of the following statements is NOT true for a project coordinator ?




Question 18

The sponsor has just signed the project charter and assigned you as a project manager to oversee a project to implement a simulator for a local golf club. What would you do FIRST as the project manager ?




Question 19

6. At your project, EV = $130,500 ; PV = $125,000 ; and AC = $129,000. Which one the following statement is true ?




Question 20

Which one the following statement is FALSE about the project management information system (PMIS) ?




Question 21

10. Stakeholder management necessitates all of the following EXCEPT :




Question 22

3. Formal written correspondence with customer is required when :




Question 23

1 . Which of the following is NOT a tool used to manage the stakeholder engagement ?




Question 24

6. You are planning to hire a third-party to perform a schedule or random structure review to determine whether your quality management activities comply with organizational an project process, policies, and procedures. All of the following will be done in this quality audit EXCEPT :




Question 25

3. Which one of the following is NOT true about a cost reimbursable contract ?




Question 26

7.A project manager is in the process of ensuring that the information needs of the project stakeholders are met by monitoring and controlling communication throughout the project life cycle




Question 27

To control the schedule, a project manager is reanalyzing the project to predict project  duration. She does this by analyzing the sequence of activities with the LEAST amount of scheduling flexibility.  What technique is she using ?




Question 28

9. A project  manager is in Develop Project Team process focusing on enhancing project performance by building a sense of team and improving competencies, team interaction, and overall team environment. While referring to Tuckman's model, she notices that the greatest level of conflict in the five different stages of team building is most likely to appear in which of the following stages :




Question 29

7. You have identified several problems along with their causes in your web-based application development project. Which one of the following have you probably used to show the problem and its causes and effects ?




Question 30

5. In a fixed price incentive fee contract, the target cost is estimated at $250,000 and the fee at $35,000. The actual cost came to be $210,000, since there was a cost saving, the seller shares the saving at a 70/30 ratio ( 70 % to the buyer and 30% to the seller). What the final fee and final price ?




Question 31

During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of the work packages ?




Question 32

10.You are the project manager of a network replacement project for a 40-floor office building. You plan to hire a contractor to pull the old cable out and then install the new cable. The work has to be done in such a way to have minimum to zero disruption to the tenant organization during business hour, hence you need to hire a well experience reputed firm. You contracted the procurement department to develop a list of firms that have the capability to do work. What are you referring to ?




Question 33

Which one of following PMO structure mostly serves as project repository., plays a consultative role, and usually has a low level of control over projects and programs ?




Question 34

Which one of the following is FALSE about change management in a project ?




Question 35

8.You are in the Manage Stakeholder Engagement process and are focused on meeting and exceeding the stakeholders' expectations by continuously communicating with them, clarifying and resolving their issues., addressing their concerns, and improving project performance by implementing their change requests. Which of the following is a tool & techniques used in this process ?




Question 36

3. Quality is :




Question 37
  1.  A CPI value of 1.20 and an SPI value of 1.30 for a project mean which of the following ?



Question 38

7. You are in the Plan Resource management process to create on overall staffing management  plan by identifying the availability of resources and those resources' skill levels. Which of the following is NOT a tool &  technique in this process ?




Question 39

When should the Validate Scope process be done ?




Question 40

Which of the following  process group serve as input to each other ?




Question 41

In this kind of phase-to-phase relationship, the subsequent phase may begin before the previous phase is completely finished although but it may increase risk and result in some rework.




Question 42

As a project manager for a major data center upgrade at your company headquarters, the sponsor has handed you a project charter. What should you do next as the first step ?




Question 43

9. As a project manager, you are trying to decide the trade-offs between quality and grade in your project. Which one of the following is correct with respect to a product or a service performed ?




Question 44

8. You are in the Monitor Risk process of identifying, analyzing, and planning for newly arising risks, keeping track of identified risks, reanalyzing existing risks, monitoring trigger conditions, monitoring residual risks, and reviewing the execution and effectiveness of risk response. Outputs from the Monitor Risk process include all of the following EXCEPT :




Question 45

Which of the following is FALSE about analogous estimating ?




Question 46

5. Commonly done in conjunction with manage stakeholder engagement process, what is another process called ?




Question 47

8. A project manager is overseeing a complex custom CSM solution that has rigorous quality standards and high schedule constraints. The project manager just found out that one of the key deliverables in the project was not completed because the team member responsible dor it was assigned to another higher-priority project by her functional manager. Who will be the person for the project manager to address the issue with this kind of situation ?




Question 48

4. A project manager has six stakeholders during requirement gathering phase but the number increase to eleven in the design phase. How many additional channels communication were added at design phase ?




Question 49

3. You are in the project manager of a construction project that will take six months to complete and will cost $75,000 / month. At the end of third month, you are asked to find out the cumulative SPI for the project. While reviewing, you found that you have spent $80,000 in the first month, $72,000 in the second month, and $75,000 in the third month. And also found that project was 15% complete at the end of 1st month, 35 % complete at the end of 2nd month, 45 % complete at the end of 3rd month. If you planned to complete 50% of the work by this time, what is the cumulative SPI at the end of month three ?




Question 50

Which one of the following estimating techniques uses mathematical models based on historical records from other projects and can produce higher levels of accuracy ?




Question 51

What is the meaning of Perform Integrated Change Control




Question 52

3. You have thirteen stakeholders in the construction project that you are overseeing. Your initial study about these stakeholders tells you most of them will  actively support your project to be successful, but you have couple of stakeholders who may adversely impact your project. When do you think these stakeholders will have the most influence on your project ?




Question 53

A project just initiated under a contract in your organization, and you were assigned as the project manager. You were expecting a statement of work (SOW), which will describe the business need, product scope, and other elements. In this case, from whom should you expect the SOW ?




Question 54

Which of the following is NOT a typical characteristic of a project management office (PMO) ?




Question 55

6. A project manager is in the process of making relevant information available to project stakeholders in a timely manner as planned. The project manager is involved in which of the following processes ?




Question 56

Which of the following is NOT a tool and technique used in the Define Scope process ?




Question 57

10. You are in Plan Risk Responses process of developing options and actions to reduce threats enhance opportunities to your project objectives. The tools & techniques of the  Plan Risk Responses are including :




Question 58

9. Which one of the following is FALSE about TCPI ?




Question 59

In which process group does the team track, measure, inspect, monitor, verify, review, compare, and regulate the progress and performance of the project; ensure that plan is working; identify any areas in which changes to the plan are required; and initiate the corresponding changes ?




Question 60

Which one of the following process group consists of iterative and ongoing processes to establish the total scope of effort, to define the project the objectives, and to identify the course of action required to attain those objectives ?