This quiz will submit in:






Question 1

8. You asked one of your team member about the schedule variance (SV) for one of the key deliverables. He mentioned that he is behind the schedule but there would not be a cost variance. Which of the following is NOT true in this case ?




Question 2

While managing a data recovery project, you are performing the following activities : comparing actual project performance against the project management plan : analyzing, tracking, and monitoring project risks ; assessing performance to determine whether any corrective or preventive actions are required; providing information to support status reporting; monitoring implementation of approved changes; providing forecasts to update current cost and schedule information.       Which process are you in this time?




Question 3

Which one  of the following is NOT a planning process  ?




Question 4

A project manager wants to determine how his project is doing the end of sixth month. The actual total expense of the project is $720,000. The planned budget for this length of the time was $600,000. He finds that :




Question 5

7. You are in the Plan Stakeholder Engagement process of defining an approach to manage stakeholders throughout the entire project life cycle as per their interest, impact, importance, and influence over the project. Which of the following is an input to this Plan Stakeholder Management process ?




Question 6

Which one of the following is TRUE about power of the project managers in different organizational structure ?




Question 7

8. A project manager is overseeing a complex custom CSM solution that has rigorous quality standards and high schedule constraints. The project manager just found out that one of the key deliverables in the project was not completed because the team member responsible dor it was assigned to another higher-priority project by her functional manager. Who will be the person for the project manager to address the issue with this kind of situation ?




Question 8

8. Lars is  a project manager overseeing an online age verification application for one of the very important clients for this organization. Three months in the project, Lars got a call from the client who informed him that they would end the contract due to a change in business direction. The client also discussed the compensation that the seller's organization is offering to Lar's organization for the work completed so far. This is an example of which one of the following ?




Question 9

Which one of following PMO structure mostly serves as project repository., plays a consultative role, and usually has a low level of control over projects and programs ?




Question 10

6. Which of the following should be included in the project charter ?




Question 11

3. Which one of the following is NOT true about a cost reimbursable contract ?




Question 12

The organization has to make an initial investment of $250,000 with expected cash inflows of $75,000 in the first year and $25,000 per quarter thereafter for the first project. The second project has a payback period of thirty-five months. Which project should the selection committee recommend ?




Question 13

The scope baseline, which consists of the scope statement document, the WBS, and the WBS dictionary, is used as an input in all of the following processes EXCEPT :




Question 14

Which of the following is a KEY output of the Validate Scope process ?




Question 15

When should the Validate Scope process be done ?




Question 16

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process ?




Question 17

9. Which one of the following will NOT be considered a valid way of reducing risks in your project ?




Question 18

5. Commonly done in conjunction with manage stakeholder engagement process, what is another process called ?




Question 19

Which of the following normally provides the summary milestone schedule ?




Question 20

While reviewing one of the activities of team member, you found out that the activity has an early start of days 5, an early finish of day 12, a late start of day 15, and a late  finish of 22 day. The team member tells you that he needs an additional four days to complete the activity due to various reasons he can think of. Which one of the following statements is TRUE ?




Question 21

9. As a project manager, you are trying to decide the trade-offs between quality and grade in your project. Which one of the following is correct with respect to a product or a service performed ?




Question 22

1 . A control chart helps the project manager :




Question 23

Project A has net present value (NPV) of $30,000, will take 5 years to complete, and the associated cost $10,000. Project B has NPV of $60,000, will take 3 years to complete, and the associated cost $15,000. Project C has NPV of $80,000, will take 4 years to complete, and the associated cost $40,000.  Which project will you pick ?




Question 24

A project's approved budget is $250,000 and planned budget to date is $150,000. What will be the Schedule Variance when Schedule Performer Index is 0.8 ?




Question 25

To control the schedule, a project manager is reanalyzing the project to predict project  duration. She does this by analyzing the sequence of activities with the LEAST amount of scheduling flexibility.  What technique is she using ?




Question 26

5. As project manager, Henry is cognizant of the importance of effective communication, and he always makes sure that he has the proper physical mannerism, such as facial expressions, hand gestures, and body language, while conveying a message. He is also particularly observant to pitch and the tone of his voice, and he tries to receive comments and feedback from the receiver while communicating. What percentage of Henry's message is sent through nonverbal communication ?




Question 27

7. You are in the Plan Resource management process to create on overall staffing management  plan by identifying the availability of resources and those resources' skill levels. Which of the following is NOT a tool &  technique in this process ?




Question 28

3. You will be overseeing a project to develop a smartphone application. While analyzing your project, you identify that there is a 55 percent probability of making $120,000, a 45 percent probability losing $55,000. What does $41,250 represent in this case ?




Question 29

1  . All the following statements about change control are incorrect, EXCEPT :




Question 30

7. Your recently took over a project another project manager who left the organization. You find out that the project has a BAC = $45,000; PV = $30,000; cumulative = $25,000 ; cumulative EV = $24,000. You decided to perform a forecasting analysis and calculated the values for EAC, ETC, and VAC. Which of the following is NOT true ?




Question 31

9. You  have been managing a multi-year construction project for one of your most important clients. You requested your lead business analyst to develop a reports that will capture project results for last four years and illustrate whether project performance is improving or deteriorating. You are interested in which of the following reports ?




Question 32

10. You are in Plan Risk Responses process of developing options and actions to reduce threats enhance opportunities to your project objectives. The tools & techniques of the  Plan Risk Responses are including :




Question 33

2. A project had a list of identified risks. This list was the risks register. Where can one find the high-level risk ?




Question 34

2. The primary purpose of the stakeholder register is :




Question 35

10. Stakeholder management necessitates all of the following EXCEPT :




Question 36

9. Which one of the following is FALSE about TCPI ?




Question 37

10. A project manager involved in the Estimate Costs process in the early phase when a limited amount of detail was available. The range was $75,000 to $200,000, and actual cost come to be around $150,000. What would you call such an estimate ?




Question 38

10. You were informed by management that an external audit team will be auditing your project to make sure that the project complies with standard organizational project management policies and procedures. During the audit, the key auditor wants to review the training plan for the team members as well as their certification requirements. You should refer the auditor to which of the following ?




Question 39

All of the following are examples of organization process assets EXCEPT :




Question 40

5. If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV) ?




Question 41

A project just initiated under a contract in your organization, and you were assigned as the project manager. You were expecting a statement of work (SOW), which will describe the business need, product scope, and other elements. In this case, from whom should you expect the SOW ?




Question 42

Which one of the following is FALSE about change management in a project ?




Question 43

8. A project manager overseeing an ERP implementation project planned to distribute large volumes of information about the project to a large audience. He decided to post the information in an online knowledge repository for access at dicreation of stakeholders. This type of communication method is known as :




Question 44

During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of the work packages ?




Question 45

6. You are planning to hire a third-party to perform a schedule or random structure review to determine whether your quality management activities comply with organizational an project process, policies, and procedures. All of the following will be done in this quality audit EXCEPT :




Question 46

5. The MOST common cause of conflict on a project are schedules, project priorities, and :




Question 47

6. A project manager is in the process of making relevant information available to project stakeholders in a timely manner as planned. The project manager is involved in which of the following processes ?




Question 48

if the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity ?




Question 49

1  . All of the following forms of power derivied from the project manager's position, EXCEPT :




Question 50

Sometimes a project coordinator is an assigned role of organization. which of the following statements is NOT true for a project coordinator ?




Question 51

3. Quality is :




Question 52

7. Which of the following is the process of documenting project purchasing decisions, specifying the approach, defining selection criteria to identify potential sellers, and putting together a procurement management plan ?




Question 53

You are managing a group of related or unrelated projects or programs and other work and achieve specific strategic business objectives and goals. You are a................




Question 54

4. You are asked by management to select a contract type that will obligate the seller to accept all liability for poor workmanship, engineering errors, and consequential damages in the project. Which of the following contact types will you select ?




Question 55

5. Monitoring specific project result to determine if they comply with relevant quality standards and identifying ways to eliminate causes of inadequate result is :




Question 56

1  . Which of the following is driven by the organization's risk tolerance ?




Question 57

All of the following should be done during the closing process group EXCEPT :




Question 58

4. A project manager has six stakeholders during requirement gathering phase but the number increase to eleven in the design phase. How many additional channels communication were added at design phase ?




Question 59

Which one of the following are the unapproved and undocumented changes and what occurs when to the scope are not detected early enough or are not managed ?




Question 60

In which process group does the team track, measure, inspect, monitor, verify, review, compare, and regulate the progress and performance of the project; ensure that plan is working; identify any areas in which changes to the plan are required; and initiate the corresponding changes ?